LEVEL 1, 2 & 3 Post-construction cleaning service

Level 1

Clean Construction

During Level 1, cleanliness begins to take on more importance. Conduct daily and hourly cleanups using vacuums and start using a daily cleaning service. There should be no unnecessary trash or debris in the cleanroom area and you should use multiple rugs as well as sticky mats to prevent dirt from entering. This is also the stage to conduct particle counts.

LEVEL 1, 2 & 3 Post-construction cleaning service

Level 2

Pre Cleanroom Construction

In Level 2, control and limit access to the cleanroom area and establish a smock room/airlock for entry/exit with an air cleaner. Workers must wear booties in the area and use sticky mats on floors. No wood, cardboard or paper allowed in the area. A HEPA vacuum is required for cleanup after all cutting/drilling in the cleanroom and the air systems should be on, but not the filter fan units.

LEVEL 1, 2 & 3 Post-construction cleaning service

Level 3

Active Cleanroom Construction

Level 3 is for finishing details and is the most restrictive. It includes all the precautions of Level 2, plus several additional steps. Workers must use a designated smock room and have limited access at this stage. Before entering the cleanroom, workers must be fully smocked, including wearing lab coats or coveralls, hair/beard nets, booties and gloves and mask. The recirculation air system should also be employed to continuously clean the air.

LEVEL 1, 2 & 3 Post-construction cleaning service

Not only do Vibraclean GMP cleaners meet the standards outlined in the Scope of Works, they complete their work in the agreed time frame to avoid project delays. All Vibraclean GMP cleaners arrive outfitted with the correct Personal Protective Equipment (PPE).

After post-construction cleaning, the room is ready is for pre-validation cleaning to further reduce particle and residue levels to within desired operating parameters and to disinfect the room, if required.